V/Line – Otway Road Composite Bridge
There are numerous engineering companies that specialise in either steel bridges or concrete components. Brunton are experts in composite structures – a combination of these two materials to make the structures work in smart ways. Composite bridges allow for structure installation that reduces disruptions to external stakeholders.
CLIENT  |  V/LINE
CATEGORY  |  STRUCTURAL
V/Line engaged Brunton to build a structurally sound bridge for Otway Road in Warrnambool, Victoria.
Our Solution
- Brunton completed the project in 8 weeks. 
- The team fabricated two 1200 WB girders and several cross-girders with welded shear studs. They also constructed a pre-cast concrete desk that they can separate from the shear studs. 
- Brunton checked that the bridge was up to standards before the team transported them to the site. They worked with VicRoads and local councils to get permits for transporting over-sized cargo within the state. 
- The team successfully: - delivered a 35-tonne steel structure on an oversized load from Melbourne to Warrnambool 
- transported a 40-tonne concrete structure to the site. 
 
- Brunton lifted the steel up first, then overlaid the concrete on top to create a composite bridge. 
 
                         
             
                 
                 
                